ARC Deadlines: When the Board Doesn't Answer in Time
architectural-reviewarchoa-governanceself-managed-hoahoa-board

ARC Deadlines: When the Board Doesn't Answer in Time

Where an HOA's architectural approval deadline comes from, what deemed-approval and deemed-denial clauses do, and the written routine that keeps the board's record clean.

Doug Wright

Say an owner turns in a fence request and then hears nothing. The contractor wants a start date, and the owner starts asking whether silence means yes. The HOA architectural approval time limit decides that moment: whether the owner can build, and whether the board can still say no.

The architectural review committee (ARC) owns that clock. What the architectural review committee is and what it controls explains the ARC itself and where it gets its authority. For intake, review and denials in general, see how to handle HOA architectural review requests faster.

Finding the deadline in your documents

Start with the declaration of covenants, conditions and restrictions (CC&Rs). The article that creates the ARC often says how long it has to respond, when that period starts, and what follows if it ends without a decision. Some declarations state the period themselves. Others leave it to architectural guidelines the board adopts.

Order matters when those documents disagree. Nolo's overview of an HOA's governing documents puts the CC&Rs at the top of the stack: when another governing document conflicts with them, the CC&Rs control and the conflicting provision is "considered invalid".

A stack of thick binders holding an association's governing documents

Photo by Pixabay on Pexels

For the ARC, a guideline, an ARC habit or a line on the request form can't shorten or stretch a deadline the declaration sets. If the CC&Rs give the ARC a fixed period and the guidelines say something different, plan around the CC&Rs and fix the guidelines at the next board meeting.

State law can add its own requirements on top. Your declaration and your state's statutes, read together, set what applies to your community; read both before the next request arrives.

Deemed approval and deemed denial clauses

Some declarations carry a deemed-approval clause: if the ARC doesn't answer within the stated period, the request counts as approved. Some carry the opposite, a deemed-denial clause, where silence counts as a no. Some say nothing about it.

The two clauses put the risk in different places. Under deemed approval, a missed deadline can let an owner go ahead with a change the ARC would have turned down, and the board may have little room to object once the work is built. Under deemed denial, the owner absorbs the delay, and a silent denial gives the owner no reason and no guidance on what to change.

Read the exact wording. Some clauses attach conditions, such as a requirement that the application be complete, or that the owner send a written follow-up before the period runs out. Those conditions decide whether the clock ever started. An unclear clause, or a deadline that has already passed on a live request, is a question for the association's attorney before anyone answers the owner.

What California requires of the procedure

California is one state that writes timing into statute. California Civil Code section 4765 applies where a common interest development's governing documents require association approval before an owner makes a physical change to their separate interest or the common area. It requires a procedure that is "fair, reasonable, and expeditious," included in the governing documents, with prompt deadlines and a stated maximum time for a response to an application or a request for reconsideration.

The same section requires a decision made "in good faith" and in writing. A disapproval must explain why the change was disapproved and describe the procedure for reconsideration by the board. If the change is disapproved, the applicant is entitled to reconsideration by the board at an open meeting, unless the board itself, or a body with the same membership, made the decision at a meeting that met California's open-meeting rules.

That statute governs only the California communities it covers. Its elements still make a useful checklist for any ARC: a written procedure, a stated response time, a written decision with reasons, and a route to reconsideration.

Why every request needs a written, dated decision

A deadline only means something if someone can show when it started and when it stopped. The written decision is that proof. It shows when the application arrived, when it was complete, when the ARC decided, and what it decided.

Without that record, a missed deadline is the owner's argument. The owner says the request sat past the deadline, an ARC member remembers calling back, and nobody can show either one. With a dated written decision in the file, the board can point to the page.

The minutes belong to the same record. When the board acts on an ARC recommendation or hears a reconsideration, the minutes should show the request, the decision and the date. What HOA meeting minutes should include sets out the format.

A calendar page with a date pinned and a pen beside it

Photo by Towfiqu barbhuiya on Pexels

Those files can come back later. An owner who disputes a decision may ask to see the request, the correspondence and the decision, and the board will want to produce them in order. The rules on what your board must provide on a records request apply to that file.

A deadline routine the ARC can run

Adjust each step below to what your own documents say.

  1. Date-stamp every request the day it arrives, whether it comes by email, web form or paper.
  2. Check it for completeness right away. If the documents let the clock start from a complete application, record the date it became complete.
  3. Ask for missing items in writing, note the date you asked, and keep a copy.
  4. Put the deadline on a calendar the whole ARC can see, with a reminder well before the last day.
  5. Decide in writing before the deadline. If the ARC needs more time and the documents permit an extension, request or grant it in writing before the period ends.
  6. Send the decision the way the documents require, and record it in the minutes when the board acts on it.

Run the same routine on every request. A deadline the ARC meets for one owner and misses for another invites a complaint about fairness.

The paperwork side in HOA-OS

HOA-OS is software for the paperwork side of this routine. The board sets up an ARC committee workflow that puts each homeowner change request in front of the ARC, and builds its request form with the form builder, which has a date field for the owner's planned start date, file upload for drawings and a signature line. New requests show up in a submissions inbox. Document storage holds the declaration and the guidelines with the deadline language. The deadline stays on the board's own calendar, and the decision stays with the board.

Sources

Related Reading

A request left unanswered keeps its clock running, and some declarations turn that silence into an approval no one on the ARC ever gave.